Infrastructure

Question by: 
Hon Brett Herron
Answered by: 
Hon Tertuis Simmers
Question Number: 
6
Question Body: 

With reference to land released for the purpose of housing development:

(a)How many parcels of land have been released in the last 18 months for the purpose of housing development, (b) in what stage of the development process are these parcels of land, (c) how much funding is being allocated to each parcel of land for development, (d) what is the timeline for development on these parcels and (e) how many social housing units, if any, are being proposed?

Answer Body: 

 

  1. Five
  2. Leeuloop – developer appointed

Founders Garden – developer procurement

10 on Fort Wynyard [Helen Bowden] – predisposal consultation

Provincial Pavement Testing Lab - developer procurement

353 on Main [Tafelberg] – Land Use Management and Heritage statutory processes

  1. project specific budgets are not allocated as the Department must fund the varying costs of obtaining the necessary development rights and of taking the development to market.
  2. Three years following handover to the developer
  3. Leeuloop – 363

         Founders Garden – 1185

         10 on Fort Wynyard – 302

         Provincial Pavement Testing Lab – Affordable rental only

         353 0n Main – 220

 

Date: 
Thursday, May 7, 2026
Top